Some New Faces Around The Square

The Restoration Programme is assessing every aspect of Dolphin Square to meet the demands and expectation of London living in the 21st Century from the use of space and energy to the care of our biodiverse environment. To ensure we appropriately and responsibly assess every aspect, our ongoing surveys and inspections span the length and breadth of the entire estate and gardens.

The Programme Has Reached an Important Milestone

With the necessary planning consents secured from Westminster City Council, the comprehensive transformation of Rodney, Duncan, and Beatty Houses at Dolphin Square is now in progress. This includes ongoing works to refurbish apartments, upgrade utilities and services, and install new windows. The relocation of Duncan and Beatty House residents to temporary accommodations within the estate marked a significant milestone, facilitated by our dedicated moves team to ensure a smooth transition. Gathering valuable feedback from residents, we strive to enhance the relocation experience for future phases. The meticulous 'strip out' phase, focusing on environmental sustainability, involves the careful removal and recycling of outdated mechanical services, radiators, and electrical wiring. This eco-conscious approach aligns with our environmental targets, achieving a remarkable 98% recycling rate. Furniture and homewares from Rodney's serviced apartments found new homes through donations to local charities and community organizations, creating a positive impact within the local community.

Restoration Programme Indicative Timeframe —2021 - 2029
Phase 1 Estimated Start Estimated Completion
Duncan House September 2021 June 2024
Rodney House May 2022 December 2024
Beatty House July 2022 December 2024
Phase 2 Estimated Start Estimated Completion
Hood & Keyes House Mid 2024 Mid 2025
Collingwood House Mid 2024 Early 2026
Frobisher House Early 2025 Early 2026
Grenville & Drake House Mid 2025 Late 2026
Phase 3 Estimated Start Estimated completion
Howard House Late 2026 Mid 2027
Nelson House Mid 2027 Mid 2028
Hawkins & Raleigh House Early 2028 Early 2029

House Refurbishment Complete in 2029